Port of Saint John Modernization Project, Saint John, NB

project photo

GEMTEC completed Quality Assurance and Quality Control testing for multiple phases of the Port of Saint John West Side Modernization Project. Our work included field testing of over 35,000 cubic metres of concrete placed in multiple 24-hour continuous slip forming operations. Over 2,800 concrete cylinders were cast and tested for compressive strength over a 6-month period.

Services provided over various phases of the project include:

  • Concrete testing (lab and field)
  • CCTV Camera inspections for rock socketed caissons
  • PDA testing
  • Grout testing
  • Laboratory testing of asphaltic concrete
  • Aggregate testing (lab and field)
  • Geotechnical and materials engineering support services